Key Features
- Project consists of reconstructing 0.8 Km of 2-lane rural road to a 4 and 5 lane urban arterial road, connecting Mayfield Road to a new urban development area and incorporating a recently constructed 4 lane bridge across Highway 410.
- New storm sewers constructed as part of the project outlet to existing storm water ponds and wetland.
- Project includes a multi-use trail in the west boulevard.
- Most overhead and buried utilities require relocation to the new boulevards.
CFA completed the detail design and contract administration for the widening and reconstruction of an 800 metre stretch of Kennedy Road (from Mayfield Road to the southern limit of the Mayfield West Community Development Area) and the redesign of an intermediate intersection in Caledon. The $3 million project also included a detailed stormwater management and mitigation plan because of the project’s proximity to the Heart Lake Wetland and Etobicoke Creek.
Kennedy Road Widening and Reconstruction from Mayfield Road to the Southern limit of the Mayfield West Community Development Area. Between 2014 and 2015, CFA completed the detail design and contract administration for the widening and reconstruction of an 800 metre stretch of Kennedy Road (from Mayfield Road to the southern limit of the Mayfield West Community Development Area) and the redesign of an intermediate intersection in Caledon. The $3 million project also included a detailed stormwater management and mitigation plan because of the project’s proximity to the Heart Lake Wetland and Etobicoke Creek.